|
|
Home > About
SOFIA > History of SOFIA
History of SOFIA |
| |
|
| |
| 2008 |
| October |
Primary Mirror reinstalled into SOFIA. |
| June |
Primary Mirror coated for first time at NASA Ames Research Center. |
| April |
Telescope Primary Mirror removed in preparation for coating |
| March |
SOFIA Line Operations conducted in Palmdale, CA at the Dryden Aircraft Operations Facility. A team of scientists, engineers, and staff from ARC, DFRC, USRA, DSI, DLR, and MAN collaborated on a series of tests of the SOFIA telescope assembly and software |
| Jan |
SOFIA Visits Ames Research Center on the way to its permanent home at the SOFIA Operations Center, located at the Dryden Aircraft Operations Facility (DAOF) in Palmdale, CA. |
| 2007 |
| May |
SOFIA’s 747 flown to Dryden Flight Research Center, at Edward AFB in California for systems installation and integration and additional flight testing
|
| |
SOFIA Re-Dedicated as "Clipper Lindbergh" at Dryden Flight Research Center |
| April |
SOFIA Completes First Flight in Waco, TX |
| 2006 |
| August |
NASA PMC (Program Management Council) chooses Dryden Flight Research Center to complete systems installation and integration and conduct flight tests of the flying observatory; SOFIA Program Office responsibility relocated to DFRC. Under new Program structure DFRC has responsibility for the "Platform Project" (e.g., the aircraft), and ARC has responsibility for "Science Project".
|
| 2005 |
| July |
FORCAST Instrument tested at Palomar. |
| (on-going) |
Fuel tanks Checked |
| April-May |
Installation of Lower Flex Door and Aperture Assembly |
| Feb |
Landing Gear Checked |
| Jan |
Installation of Upper Rigid Door |
|
2003 |
| Nov |
SOFIA
Telescope Floats! |
| |
TA activated for course drive movements |
| |
Science Instrument Mounting Flange and TA Balancing Assembly
mounted to Suspension Assembly |
| |
Secondary Mirror and Spider Vanes attached to Metering Structure |
| |
TA Metering Structure installed in aircraft |
| |
Telescope Suspension Assembly installed in aircraft |
| |
Aircraft downjacked
onto landing gear |
| 2002 |
| |
All skins mounted on aircraft |
| |
Modified aircraft structure completed |
| |
Cavity Bulkheads completed |
| |
All components of Cavity Door in
fabrication |
| |
CDR of Data Archive System successfully
completed |
| |
Mirror Coating facility in SSMOC
tested and working |
| |
FLITECAM (SOFIA Science Instrument)
has successful "first light" at Lick Observatory |
| |
Telescope arrived in
Waco from Germany |
| 2001 |
| |
AIRES instrument cancelled |
| |
Mounting of skins on aircraft proceeding |
| |
HAWC Critical Design
Review (CDR) completed |
|
2000
|
| |
SOFIA CDR successfully completed
Incremental telescope CDRs completed
Telescope cradle completed
Completion of Software Final Design Review
Incremental Integration of USRA/DARA telescope software in
Munich
First cut of airplane cavity skin
Forward bulkhead floor assembly completed
Cavity aft bulkhead installed
Aircraft stringer and reinforcements installed
Cavity sill beams modified
Galley CDR completed
Aircraft ceiling raised for telescope assembly
MCS Build 2 completed
Conceptual Design Review for SAFIRE completed
Data Cycle Core System demonstrated at Rochester Institute
Of Technology
FORCAST and FLITECAM CDRs completed
Flight Scheduler Preliminary Design Review (PDR) completed
EPO presents IR Airborne Teacher's Workshop in Phoenix
SIRTF/SIM/Astrobiology EPO collaboration launched
Science Observing Scenarios briefed to Steering Committee
First metal (structural member) cut on aircraft
Telescope assembly CDRs completed
SOFIA "4 Minute Features" to
be shown on United Airlines in-flight News videos
|
top of page
| 1999 |
| |
Four calibrated test flights with
maneuvers give confidence to flight stability load distribution,
and pressure responses
Design efforts continue for modified
aircraft structures and subsystems
Telescope Assembly Incremental
Design Reviews begin
Telescope Assembly Mock-up installed
Mission Control System Build 1
completed
Mirror-coating contract awarded
Hanger N211 extensively modified
demolition and steel fabrication, roof
Airplane water, oxygen, air conditioning
systems modified
Internal shoring installed on
aircraft from mock-up Section 46
Telescope Assemble CDRs begin
Science Observing Scenarios working
group meets
Final design of observatory Layout
of Personnel Accomodations (LOPA) submitted
Aircraft Mass Simulator designed
Liquid nitrogen injection system
designed
EPO airborne astronomy presentations
in Idaho, Michigan, California
|
| 1998 |
| |
SOFIA PDR completed
Design efforts under way for modified aircraft structures
and subsystems
Conceptual Design Reviews for ARIES, HAWC, FORCAST, FLITECAM,
HIPO, FIFI-LS, GREAT, EXES, CASIMiR
Data Archive and Data Cycle Group formed
Ames Work Products development begins (Water Vapor Monitor,
Flight Scheduler)
Airplane cavity Environment Control System (ECS) designed
Rerouting of air, etc. within aircraft
Designed observatory Power Distribution System
Design work on the LOPA (floor plan) begins
Air Worthiness Manual preparations begin
Instrument Rotator designed
|
top of page
| 1997 |
| April |
SOFIA dedication ceremony held at NASA Ames
Call for Proposals goes out to the observing community
First Light Instruments
selected
US Peer Review of First Light Instrument proposals
Telescope Readiness Review completed
SOFIA (Readiness Review) (SRR) completed
SOFIA website released
|
| 1996 |
Jan |
ARC gets
new Center Director |
Mar |
SOFIA Project
Management gives briefing to NASA HQ Programs Management Council.;
ARC Space Projects Review Board given SOFIA presentation |
Apr |
U.S. SOFIA
RFP released |
June-
July |
NASA Ð DARA management
interface meetings held in Germany and in the U.S.; Proposals
received from U.S. industry teams. |
Aug |
DARA receives
proposals for TA. |
Oct |
DARA and
DLR merger begins. |
Nov |
DARA down-selects
SOFIA TA Contractor team. MAN/K-T/MAN consortium awarded fixed
priced contract for development of TA. |
Dec |
USRA team
awarded SOFIA contract for aircraft purchase, modification,
and system integration. |
| 1995 |
Feb |
Feb
SOFIA III wind tunnel test completed. |
Mar |
Non-Advocate
Review held at ARC; Industry Briefing on SOFIA Privatization
held at ARC. |
May |
Interface
meeting with DARA and German teams held at ARC. |
July |
DARA
Interim Phase B Study contracts completed by two teams: MAN/K-T
and Zeiss/Dornier. |
Sept |
Science
Symposium in Switzerland discusses SOFIA. |
Oct |
Stand-down
of KAO; ÒLive from the StratosphereÓ last flight; Boeing
747SP course given at ARC by United Airlines. |
Nov |
SOFIA
IV wind tunnel test completed; SOFIA Industry Workshop held
in Sunnyvale, CA. |
Nov-
Dec |
NASA and DARA both working on their respective RFP drafts. |
top of page
| 1994 |
Jan-
Dec |
NASA and DARA continuing to work together in attempts to get
SOFIA moving forward on both sides of the Atlantic; Science
Working Groups in Germany and in the US busy advocating SOFIA.
|
Aug |
SOFIA
II wind tunnel test for aft configuration completed. |
Sept-
Dec |
DARA
Phase B1 Studies performed by two German teams. |
| 1993 |
Jan-
Apr |
Briefings
held for various center management review panels on new
SOFIA
implementation plan, with FY94 "in-house" option proposed
APRIL Efforts under way to prepare for aft configuration
wind tunnel
test |
Apr |
In-house approach approved by Office of Space
Sciences (OSS) at Headquarters, by ARC New Business Filter
Committee, and by SOFIA In-house Implementation Plan review
committee
Headquarters Code C funding augmentation executed
for technology development work
|
June |
ARC Code R agrees to de-mothball 14 ft wind tunnel for SOFIA
test; Test entry planned for 1994
CFD model on full -SP finalized for first test run
Began locating a section 46 of a Boeing 747
"Pro-Engineer" selected as Project and Code E computer-aided
design (CAD) package
|
Aug |
Headquarters
OSS proposes recycling SOFIA as an FY95 new start to Administration/Comptroller |
Oct |
German
Space Agency indicates willingness to participate in SOFIA with
an FY96 start |
Nov |
NASA
redirects planning for an FY96 start with DARA participating
|
| 1992 |
Jan |
IR measurements made
of the Shuttle Carrier Aircraft (SCA) engine plumes using IR
cameras mounted in Lear jet |
Mar |
Kickoff
meetings for Telescope NRA studies (Lockheed Missiles & Space
Company (LMSC), Hughes, Kaman) |
Apr |
Kickoff
meetings for Aircraft NRA studies (E-Systems and Lockheed Aircraft
Services, Ontario) |
Aug |
Second
flight test on IR plume noise is made with cameras mounted inside
SCA |
Sept |
Further
options investigated to reduce total project costs, including
initiation of in-house approach study |
Nov |
Plume study
completed; aft installation feasibility verified and baseline
change confirmed |
Dec |
Final reports of Aircraft System NRA submitted; Results concur
with Ames in-house study regarding feasibility and cost savings
for the aft cavity configuration
Feasibility of modifying existing SOFIA wind tunnel model
for an aft cavity investigated
In-house implementation
plan study fully underway; telescope, consoles + electronics,
part of aircraft mod brought in-house to ARC
|
top of page
| 1991 |
Jan |
NAS Decade Survey (Bahcall
committee) Report recommends SOFIA as the top priority moderate
new mission for NASA
|
Mar |
DARA's budget uncertain
Second wind tunnel entry planned for January 1992 to refine
door design trade space
|
Apr |
Development on three
cavity door configurations for the wind tunnel model underway
at ARC |
May |
With the realization of possible
DARA budget cuts, SOFIA plans for FY92 start with an all U.S.
program, with optional help from DARA in FY94 MAY Aircraft Modification
Contractors road trip: Find out what companies have interest/capability
to perform the SOFIA aircraft modification |
June |
Cavity Cooling System
in-house study report finished |
July |
In-house descope studies
begin, to try to reduce total SOFIA cost; 5 cases considered:
1 thru 4 are telescope cost reduction options/case 5 considers
an aft cavity location to reduce aircraft modification costs |
Sept |
NASA Research Announcement (NRA) planned as procurement method
to fund multiple studies with U.S. contractors to develop
a U.S. option for the telescope
Descope studies completed; Only case 5, reducing the aircraft
modification cost by about 40%, which in turn reduces the
total cost of the project by 12%, appears to be viable approach,
since the science impact is moderate.
Planned January 1992 wind tunnel test indefinitely postponed
because of new, aft configuration selected for further study
NRA planned for two aircraft studies to confirm the feasibility
and in-house estimate of savings for aft installation
|
Oct |
Computational Fluid Dynamics (CFD) studies on aft cavity
are initiated
NRA released for Telescope System studies
Aft installation studies begin to analyze background IR noise
caused by engine exhaust plume
Aft cavity location adopted as new baseline for the Aircraft
System, pending study results
|
Dec |
NRA released for Aircraft
System study |
top of page
| 1990 |
Mar |
SOFIA wind tunnel model tests start
|
Apr |
Shear layer control device is developed
for wind tunnel model |
May |
German Space Agency, DARA (Deutsche
Agentur fuer Raumfahartangelegenheiten) budget cuts begin |
June |
Non-Advocate Review is held for SOFIA in accordance
with the agency's new start-gate policy; SOFIA deemed ready
to proceed to development again and recommended for 1992 start
Preliminary engineering study of SOFIA Ground
Support Facility at new site underway
Aircraft System modification procurement activities
underway, Source Evaluation Board (S.E.B.) established
|
July |
Wind tunnel tests successfully completed; A low drag passive
shear layer control device derived, that exceeds performance
expectations
Redefining of cavity door begins, to incorporate wind tunnel
test results
In-house studies of Telescope Sub-Systems begin
|
Oct |
Consoles and Electronics System (CES) mock-ups evaluated
Reunification of Germany, requiring reduction of German government
agencies' budgets
|
| 1989 |
Jan |
JANUARY Telescope diameter fixed at 2.5 meters
by NASA HQ/DFVLR agreement
|
Feb |
Wind tunnel model design complete
and fabrication begins |
May |
Headquarters establishes Science Working Group (SWG) as follow-
on to SOFIA Science Consulting Group
Recommendation to proceed with development from Space Science
and Applications Advisory Committee (SSAAC)
Project Definition Review completed at ARC; Found SOFIA well
planned and defined and approved the project to proceed into
the development phase contingent on a successful completion
of wind tunnel test
|
June |
Draft MOU for development
and operations phases reviewed by Ames, headquarters (Code S,
X, and G), SWG, and the German Aerospace Research Establishment
(DLR), formerly DFVLRFabrication of wind tunnel model completed
by Microcraft; Model air-freighted to Ames. However, SOFIA wind
tunnel test start delayed to allow completion of incumbent test
|
July |
Non-Advocate Cost Review successfully completed at ARC with
NASA Headquarters participation; Affirmation of project readiness
for 1991 start; FRG listed as responsible for telescope assembly
14 ft wind tunnel breaks down: cracked turning vanes, SOFIA
test start delayed further
Definition studies completed by NASA and BMFT; Phase B complete
|
Sept |
Telescope and Aircraft System Phase
B final reviews are completed and reports published |
Oct |
Boeing re-organizes; No longer interested
in "one-of" mods like SOFIA |
Nov |
Berlin wall falls; Reunification
of East and West Germany considered |
top of page
| 1988 |
Jan |
Small IR Project Concept Review awards SOFIA
highest priority, Committee on Space Astronomy (CSAA) and
Astrophysics endorses SOFIA
|
Apr |
Phase
B Aircraft Proposal review at Boeing Military Airplanes (BMA) |
May |
SOFIA
in preliminary Office of Space Science and Applications (OSSA)
Research and Analysis FY90 budget for start of development and
acquisition of aircraft |
June |
Space and Earth Sciences
Advisory Committee (SESAC) recommends that SOFIA proceed into
definition phase
Rose Engineering under contract
to provide wind tunnel test plan and be the principal investigator
in defining the SOFIA cavity shear layer control device
|
Aug |
Meetings at Society of Photo-optical
Instrumentation Engineers (SPIE) and ARC with FRG (Zeiss)
technical experts on technology status, study issues, interfaces,
and planning
Microcraft begins conceptual
design of wind tunnel model at 7% scale
Project Readiness Review
(PRR) of SOFIA at ARC; Approval to proceed with project definition
|
Sept |
SOFIA zeroed for new start
in FY90 budget; Replanning for FY91 development starts
Requirements and interfaces
documents for definition studies completed and distributed
Resource assessment studies
completed with Electrospace Systems Inc. (ESI), E-Systems,
and The Analytical Sciences Corporation (TASC)
|
Oct |
Phase B (Definition Study)
kickoff meeting for German Telescope Assembly at Zeiss completed
Data System definition study
kickoff at ARC by Code EES
Ames project coordination meeting completed with DFVLR in
Cologne
Preliminary Design Review
of wind tunnel model completed
BMFT (Bundesministerium
fuer Forschung und Technologie), the German Ministry of Science
and Technology, issued authority to proceed with Phase B definition
studies for Telescope System
|
Nov |
Project Readiness Review
of Telescope System completed at Zeiss
Interface definition meeting
between three German telescope contractors, BMA, and Ames
completed at Zeiss
|
Dec |
Astrophysics
division/BMFT workshop completed at NASA Headquarters |
top of page
| 1987 |
Feb |
Telescope System
Phase A Study midterm review at ARC
|
Feb-
Sept |
Boeing-MAC
Phase II Study |
May |
German
Phase A studies complete |
July |
SOFIA
concept review held at ARC |
May-
Aug |
Science
Applications International Corporation (SAIC) cost study for
Aircraft System |
Sept |
Ames
Conceptual System study finished; SOFIA "Phase A System Concept
Description" (The Red Book) published |
| 1986 |
Jan |
Ames Research
Center (ARC) establishes SOFIA Study Office
|
May |
SOFIA
technology workshop at Ames; Informal examination of the SOFIA
concept and associated technical issues presented by experts
in the related disciplines |
May-
Nov |
Boeing-MAC Phase I Study; Confirms the feasibility of installing
a 2.5 meter telescope in a 747SP JULY Ames receives draft of
the Memorandum of Understanding (MOU) for Telescope System study
Statement of Work (SOW) from Germany |
Aug |
A
presentation of SOFIA is held at NASA Headquarters |
Oct |
Ames
in-house Conceptual System study begins |
Nov |
Collaborative agreement made with DFVLR (Deutsche Forschungsanstalt
fuer Luft und Raumfahrt), the German Aerospace Research Establishment
German Phase A Telescope System studies kickoff |
top of page
| 1985- 1965 |
1985 |
NASA Headquarters
allocates FY86 funding for Aircraft Modification Study; Science
Consulting Group formed; NASA headquarters (HQ), Ames Research,
and Federal Republic of Germany (FRG) representatives meet
at HQ and Germans agree to study the development of the Telescope
System
|
1984 |
Ad
hoc advocacy group of IR astronomers formed for LAT; Paper
on LAT presented; "Stratospheric Observatory For Infrared Astronomy
(SOFIA) Preliminary Feasibility Study" report issued in December;
Ames/Astronomical Society of the Pacific (ASP) Symposium:
Airborne
Astronomy (10th KAO Anniversary) |
1983 |
Success
of Infrared Astronomy Satellite (IRAS) shows need for follow-up/exploitation |
1982 |
International
Astronomical Union (IAU) Symposium : IR Astronomy; Invited discussions
of KAO and LAT |
1980 |
Concept
summary for LAT developed by KAO staff; "Three Meter Telescope
on a 747SP Platform" paper presented |
1977 |
Boeing
delivered to NASA Ames a study for a LAT in a Boeing 747SP |
1975-
1979 |
Planning
for LAT continued at low level |
1974 |
First research flight of KAO; Initial studies on larger system |
1972 |
Development
well underway on the 36-inch telescope now to be mounted
in
a Lockheed C-141 platform; Project named the Kuiper Airborne
Observatory (KAO); Greenstein report on "Large Stratospheric
Telescope" published |
1969 |
Planning
started for installation of 36-inch telescope in a CV-990; First
astronomy community interest in Boeing 747 1971 National Academy
of Sciences (NAS) Decade Survey (Greenstein) Report recommended
study of Large Airborne Telescope (LAT) |
1965-
1969 |
First
use of NASA aircraft for infrared (IR) astronomy (Convair CV-990
and Lear Jet) |
|
top of page
Page Last Updated:
October 20, 2008
|
|
 |